Good Morning!
I know there are a number of posts out there about excluding weekends, but wanted to pose another question as I feel what I am doing is sightly different. I have multiple date fields (40+). What I am doing is looking at the duration between various combinations of the dates. Time between can range between same day to 300 days out. What would be the best way to approach this?
I could isolate each combinations of dates and then use one of the methods discussed in the community. Although doable, with the number of fields I have that would be a massive task so I just wanted to reach out and see if there were any better suggestions before I put in my earbuds, turned the music up, and barreled through it!
Thanks in advance,
Brian